In the summer of 2018, as I was getting ready to join Control4 as CTO, Martin, the CEO, sent me a spreadsheet laying out how I should spend my first six months. The sheet was named “Martin’s First Stab” and said we would refine it once the start date was real. It was generous of him to take the time to build it, and it was also a list of things to do: Take the product training hands-on course, read the 2016 and 2017 board decks, meet with Finance to get a view of departmental expenditures, meet with the regional sales directors, travel with supply chain to our contract manufacturers in China, blah, blah, blah.
Every item on Martin’s list was reasonable, but none of them told me or anyone else what should be true once I had done them.
I added a second tab and called it “Charlie’s Take” (I still went by Charlie then) and subtitled it “Using Charlie’s CBTO Mental Model.” I rebuilt the plan as a grid, with Customer, Business, Technical, and Organization down the side and four dated horizons across the top, each with theme:
- 30 days, August 31, 2018: Land.
- 60 days, September 30, 2018: Understand Direction; Sense Big Problems.
- 90 days, October 31, 2018: Start Formulating Plan.
- 180 days, January 31, 2019: Ship has Turned.
Each cell had a key objective, evaluation criteria, and tactics. Where Martin’s list said to take the hands-on course and the classroom training, my 30-day customer objective was to “Know breadth of C4 solutions,” and my 60-day objective was to “Be a Control4 Home Owner.” I took that last one seriously enough that by the time I announced the job, my house had 148 Control4 lighting loads and 52 keypads in it.
A few weeks after I started, I published the plan to the whole company.
That spreadsheet is the best illustration I have of what onboarding is for.
Onboarding is kindness with dates: a written plan, built before the person exists, that tells a new hire what will be true at 30, 60, and 90 days, and that is in their hands on the first day.
Most onboarding is improvised
I have watched a lot of new hires arrive at companies that wanted them badly and then did not know what to do with them. The candidate was good, the role was real, the interviews were strong, and then the person showed up and the organization improvised, with no written expectations from the manager, no stakeholder map, no first deliverable, and no agreed way to learn the system. Three months later someone says “the new hire is not ramping fast enough”, and nobody asks what “fast enough” was supposed to mean, because nobody ever wrote it down.
I think of most of these failures as hiring failures that the company discovers late. In Hiring First. Everything Else Second I argue hiring is a lifecycle that “starts when someone first says, ‘We need a role’” and “does not end when the candidate signs the offer letter.” A manager who sees hiring as an interview process stops caring once the offer is signed, while a manager who sees it as a lifecycle cares a great deal about what happens in the new hire’s first quarter.
Write day 90 first
The most useful thing I teach hiring managers is to write a 30-60-90-day plan before they write anything else about the role, including the job description.
Here is how I put it to an engineering leader at a space company this summer, while we were talking about a recent hire whose behaviors had not fit the team:
“Before you even write the job description, create a 30-day, 60-day, 90-day plan for that employee. What are they going to do the 1st 30 days and accomplish the first day? What are they going to accomplish the next 30 days and then the next 30 days after that? And if you can’t write that down in a way where it’s really clear what they would have accomplished, then you probably don’t hire someone.”
The plan is a working-backwards artifact. When you write down what this person will have accomplished by day 30, day 60, and day 90, you have to decide which customers they will understand, which decisions they will own, which part of the system they will be responsible for, and who they will need to know. Once you can write these down in a 30-60-90 plan, the job description almost writes itself, because the title, the level, the experience you are looking for, and the evidence of excellence you want to see in a resume all follow from what the plan says the person has to do.
If you sit down to write a 30-60-90 and you cannot describe what a great person would accomplish in their first 90 days, the problem is the role, and no amount of recruiting will fix it. I would rather a manager discover that in an afternoon with a blank grid than six months after someone has joined.
The person who writes the 30-60-90 is the hiring manager. HR and recruiting can supply templates, examples, and tools that make it easier, but the plan describes the work, and the person who will manage the work is the only one who can write it well.
What does a 30-60-90?
First, it’s a grid, not a list. Like this:

An example 30-60-90 for a new VP of Product, the same plan the 30-60-90 app opens with. The criteria say what will be true; the tactics say how to get there.
The top-level rows are the four lenses of CBTO: Customer, Business, Technical, and Organization.
Each of these rows has sub-rows which are the facets that fit the role. A product leader’s Customer lens might include end customers, dealers, and third parties, while a general manager’s Business lens might include finance, goals, and strategy. I put People and Mechanisms under every lens, because every part of a job involves knowing who does the work and how the work gets done.
The top-level columns are the 30-60-90 day horizons, with the real calendar date and a theme. A real date turns “the first month” into September 10, which a new hire can put on a calendar. The theme helps the new hire focus. I love “Land” for the first 30 days for any role. For my Control4 gig I used “Understand Direction; Sense Big Problems” for 60, and “Start Formulating Plan” for 90. When I hired a senior manager at Amazon a few months earlier, I named the horizons Ramp up, Make it Your Team, and Celebrate Victories that are Yours. The theme names matter less than the fact that they describe a progression. The new hire spends the first 30 days learning the system, the next 30 contributing to real work with guidance, and by day 90 owns something real enough to show how they operate.
Each horizon has the same three sub-columns:
- Key Objectives
- Evaluation Criteria
- Tactics/Deliverables
With those row and column headers, what goes in each cell is pretty obvious.
The evaluation criteria column is the most important. Good criteria are written in the first person and describe something anyone could check. The plan I wrote for that Amazon Sr. Manager did this better than my own plan did the next summer. Under “Evaluation criteria – How do we know this is working?” it said:
“I can speak with some authority on customer, business, and technical topics relating to smart lighting, thermostats, cameras, security systems, and entertainment devices.”
“I know the as-built and proposed org design for each team and know the names/faces of all managers.”
A criterion like “I can enumerate the 15 programs and their owners” describes knowledge the new hire will have, while a criterion like “Meet with the PMs” describes an activity they will perform. Meeting with the PMs belongs in the tactics column, as one way to get to the criterion. When a plan’s criteria all start with Meet, Attend, Read, or Schedule, the author has written a welcome-kit checklist, which is exactly what Martin wrote and exactly what I slid back into.
To make this painless for you, I built the grid into an app on my website: The 30-60-90 app opens on the same grid shown above, with several templates, so you start by editing a real plan instead of facing a blank page. When you write a task where a criterion belongs, it flags the cell in amber and offers to move the line to Tactics or rewrite it as “I can…,” and before it exports your plan as a spreadsheet or a readable document, it checks the whole thing for the same mistake. Status stays hidden unless you turn it on, because the plan is a document you hand someone on day one, not a tracker.
Before day one
Onboarding starts before the new hire shows up. Before the first day, the manager should have the 30-60-90 plan written, a stakeholder map, the first one-on-ones scheduled, the first deliverables named, the learning materials collected, and a clear explanation of how success will be judged.
This is the opposite of bureaucracy, because it is the manager doing a few hours of work so that the new hire does not spend weeks guessing. Somebody (the manager, duh) chose this person over every other candidate, and the least the company can do is have a desk, a laptop, working access, and a plan waiting for them.
Day one: make it your own
On the first day, the manager hands the new hire the plan. What happens next is the part most managers skip.
In December 2017 I hired a senior manager onto my team in Alexa Smart Home, and the welcome letter at the top of his launch plan said:
“I’m a big fan of a 30/60/90 day launch plan mechanism. The idea is that the new employee owns their launch plan, but the hiring manager kicks it off. Within about 2 weeks you should take what I’ve provided here and ‘make it your own’. Edit, delete, add as you see fit as you gain more understanding of team / role. At about the two week point we’ll meet and you’ll echo the plan back to me so we can review your changes together.
Assuming we’re aligned, you’ll share the 30-60-90 plan with your peers … and anyone else you want to. This drives transparency and enables a simple way for others to know your role and scope.
The first 90 days should be intensely focused on learning about our business. You should get to know your team and your internal stakeholders, the projects they are working on, the challenges they face, and what they need from you to succeed. In those 90 days, as you do this, I’m confident you’ll accomplish great things that we’ll celebrate as early wins.”
The manager writes the first draft of the 30-60-90 because the manager knows what the role is supposed to accomplish. The new hire rewrites it because, within two weeks, they know things about the team and the work that the manager never wrote down. When they meet to review the changes, “we” end up with a plan “we” both believe in.
Echoing the plan back accomplishes two things:
- The manager learns whether the new hire understood the role, which is much cheaper to learn in week two than in month four.
- The new hire walks into week three with an agreement about what is going to happen, so the manager does not have to check on every task to know whether things are on track.
Sharing the plan with peers, which I asked for in 2017 and did myself in 2018, matters more than it seems. A plan that lives only between the manager and the new hire tells nobody else what the new person is there to do, and a published plan answers that question for everyone the new hire meets.
Those 90 days…
The first 30 days are for learning the system: the customers, the business priorities, the architecture, the team structure, the key mechanisms, and how decisions get made. The manager gives frequent feedback during these 30 days, not at the end of them.
By day 60, the new hire should be contributing to real work with reasonable guardrails. A new hire assigned toy projects learns how to do toy projects, and a new hire given a real problem with support learns the job.
By day 90, the new hire should own something real enough to show how they operate. For a senior hire, that might be a technical direction, a team mechanism, a project plan, or a proposal for how the organization should change.
Day 90 is a milestone, not a final exam
People sometimes hear “30-60-90” and imagine that day 90 is a test the new hire passes or fails. I encourage managers not to over-index on perfect accountability at day 90.
When a hire is “done” depends on the role. For an engineer joining a well-run team, 90 days might be plenty. For a senior leader taking over an organization that needs to change direction, it might be six months or a year, which is why I added Ship has Turned at 180 days in my own plan. The plan represents a hypothesis written by someone who had not met the new hire yet, so some of its objectives will turn out to be wrong, and the new hire should be rewriting those along the way rather than being graded against them.
The real power of the plan is that it gets someone off to a structured start. The new hire knows on day one what the role is for, who they need to know, what they should learn first, and what good will look like in a month. The manager has a shared document to coach against. The peers know what the new person is there to do. Most of the value lands in the first two weeks, long before anyone gets to day 90.
When you are the new hire
If you are starting a new role and your manager hands you a list of activities, the way Martin handed me his, you do not need permission to turn it into a plan. Rewrite it on the CBTO grid, in the 30-60-90 app or a spreadsheet, give each horizon a date and a name, write criteria in the first person that describe what you will know and own, and then take it back to your manager within two weeks and walk through it together. Then publish it, and publish it again if nobody reads it the first time.
If your manager hands you nothing, write the plan yourself anyway. You will learn more about the role writing that document in your first week than in a month of meetings, and the gaps you cannot fill will show you what to ask your manager.
Kindness with dates
Looking back at Martin’s list and Charlie’s Take side by side, I do not think the difference between them is effort or intelligence, because Martin cared enough to write a plan for someone who had not even started yet. The difference is that Martin’s list described what I would do, while Charlie’s Take, empty criteria and all, tried to describe what would be true. One produces a busy new hire, and the other produces a new hire who knows where they are going.
The plan comes first because writing it is how a manager figures out what the role is. It comes with dates because a plan without dates is a wish. And it arrives on the first day, already written, because that is the kindest thing a company can do for someone who just bet part of their career on it.